Building Regulations - The Approval Process

Submitting an application

If Building Regulation approval is needed an application must be deposited prior to starting work. There are two types of application for this - the Full Plans application and the Building Notice application. Information about how to make an application is on our Building Regulations - Applying for Approval page.The following notes will guide you through the process which takes place once you have submitted for your chosen route of application.

Full Plans applications
Once your Full Plans application form has been received, we will acknowledge receipt of the application and send you full guidance notes. We will then check the submitted details for compliance with the Building Regulations. All applications are checked within the statutory period of 5 weeks. We may then request additional information or amendments from you or your agent.

To allow the submission of additional information and/or amendment details, the deadline may be extended to two months from the deposit date.

Once we are satisfied that the plans show compliance with the Regulations we will issue an approval notice. If minor amendments or information is required we will conditionally approve the application to save the need for a new re-submitted application. The outstanding conditions can then be cleared when the information is available.

The main advantage of the Full Plans application is the security and potential financial saving gained by building to an approved application. You and your builder know that the work shown on the approved plans complies with the Building Regulations and so you can build with confidence.

Building work may start 24 hours after we receive the Full Plans application, although all work is carried out at your own risk until full approval is gained. Please refer to the work on site section.

top

Building Notice applications

Once your Building Notice application form has been received, we will acknowledge receipt of the notice and send you detailed guidance notes. We may ask you for additional information if we feel the project is complex and needs more detailed consideration.

The main advantage of this type of application is that full building plans and details do not have to be prepared. The Notice is not approved or rejected and so building work progresses on site without the protection of a formal approval notice. Please note that some finance houses, banks and building societies do not favour this type of application. Building work may start 24 hours after we receive the Building Notice.

Charges
Building Control is a self-financing service. Legislation requires us to set charges to recover our costs. The charges can be downloaded.

top

Planning permission

Please note that planning permission may be required before work can start on site. Please check with the Planning Department at customer.services@bracknell-forest.gov.uk for information about planning issues. You may also find it useful to visit our Pre-application Planning Advice page.

Work on Site

When you have submitted an application and you are ready to start work you must notify us at various stages of the work. This will depend on what work is being carried out and will be detailed in the guidance notes you will receive with the acknowledgement letter.

The following are the usual stages of work that we inspect:

  • Commencement of work.
  • Foundation excavations.
  • Foundation concrete.
  • Damp proof courses.
  • Floors before covering with oversite fill.
  • Damp proof membranes.
  • Drains before covering.
  • Intermediate floor structures.
  • Roofs.
  • Major structural members ie, beams and columns.
  • Occupation.
  • Completion.

In addition to the above, we will usually ask for pressure tests of all drainage, and tests of fire detection and alarm systems.

top

Requesting an inspection

If you contact us by 10am we can usually call the same day. You can request an inspection by contacting us using these details:

Bracknell Forest Council
Building Control
Time Square
Market Street
Bracknell
RG12 1JD

Tel: 01344 352000
Fax: 01344 351193
Email: Building.control@bracknell-forest.gov.uk

Alternatively, you can use our online booking form.

Completion Certificates
When work is complete we will issue a Completion Certificate free of charge. This certificate is required by solicitors as part of the house sale process to prove that the work complies with the Building Regulations.


-Listen to this page- -Listen- -Feedback on this page- -Feedback- -Print this page- Print


top

External Links

  • Bracknell Forest Council is not responsible for the content of external websites

Contacts

Skip to main content
[
Home
]
[
What's New
]
[
Sitemap
]
[
Search
]
[
Frequently Asked Questions
]
[
Website Help
]
[
Complaints Procedure
]
[
Disclaimer
]
[
Feedback Form
]
[
Accessibility
]
[
Skip to main content
]